RayGen Power Plant, Carwarp

Flagship technology demonstration with integrated solar and long-duration storage

Victoria, Australia

5 MW

Solar

2.8MW / 50MWh

Storage

17 hours

Duration

AGL

Customer

Operational

Status

Project Overview

Carwarp is RayGen's flagship technology demonstration project.

The plant, operational since 2023, provides reliable, on-demand power to the West Murray distribution network in Northwest Victoria, offering improved grid security and reliability.

The project has a commercial offtake agreement with AGL and was supported by an ARENA grant.

Carwarp is also home to an additional 1MW solar field, installed during 2025, to prove key automation tools and other technology advances.

Project Highlights

Solar Capacity

5 MW (five towers × 1MW)

Storage Duration

17 hours / 50MWh

CO₂ Savings

10,000 tonnes per annum

Homes Powered

~1,000 homes

Project Status

Carwarp began exporting solar energy to the grid in July 2022.

The project achieved 'commissioning complete' – the final project-related milestone with the Australian Renewable Energy Agency (ARENA) – in July 2023.

It has an offtake agreement with AGL.

Get In Touch

Want to Learn More About RayGen's Projects?

We welcome all enquiries, including interest in development, partnerships, employment, and media.